Solar panel installation: what happens from survey to handover

The short answer

A typical solar panel installation takes one to two days. Before that come a survey, a written performance estimate and the contract. Afterwards the installer tests the system, tells the network operator and registers an MCS certificate, which Smart Export Guarantee suppliers ask for as proof of certification.

1 to 2 daysto install a typical system, including the electrical work (Energy Saving Trust)
14 daysafter the equipment is delivered: when the right to cancel a contract signed at home usually ends
28 daysfor the installer to tell the network operator after switch-on (G98)
3.68 kWtotal AC output of the solar inverter and any separate battery inverter, single-phase supply, for install-then-notify (G98); above it, G99 first

Sources: Energy Saving Trust [1], Consumer Contracts Regulations 2013 [18], RECC [15], Energy Networks Association [24][25]. Read 13 October 2026.

How are solar panels installed?

A domestic solar panel installation runs in nine stages, from a survey of your roof to registering the system for export payments. MCS-certified installers work to the Microgeneration Certification Scheme (MCS) standards, the industry quality scheme. Two versions run side by side until 31 March 2027, the current scheme and a redeveloped one [7], so a few rules below differ by scheme.

  1. Survey and design. A competent person assesses the building and checks the roof can carry the load; an accurate shade estimate usually needs a site visit [2][4].
  2. Written estimate and quote. Before you sign, an MCS installer gives a performance estimate in a set format, which says it is not a guarantee, with the panel and inverter datasheets and a layout drawing [4]. The quote should say how long the job will take and when it can start [11].
  3. Contract and cooling-off. For a contract signed at home, or agreed online or by phone, you can usually cancel from signing until 14 days after the last of the equipment is delivered [17][18][15]. Work starts inside that period only if you ask for it, in writing or by email for a contract signed at home [19].
  4. Network permission, if needed. Larger systems, including some with a battery, need the network operator's approval before installation (the G99 process) [25][2].
  5. Scaffolding. May go up a few days before installation day [1]. Scaffolding that obstructs a pavement or road in England and Wales needs a licence from the highway authority, usually the council [31]; Medway Council, for example, says the scaffolding company or builder applies [32].
  6. Installation. Brackets, rails and panels on the roof, then the inverter and wiring. The power may be off briefly while the system is connected [1].
  7. Testing and handover. The system is commissioned to a documented procedure; you get a demonstration and a handover pack [2][5].
  8. Notifications and certificates. The installer tells the network operator, registers the MCS certificate and tells you who is responsible for the building regulations notification; if it is registered with a competent person scheme, it can self-certify the work itself [2][3][5].
  9. Export payments (Great Britain). You apply to a Smart Export Guarantee supplier with your MCS certificate or an equivalent; it provides the export meter number (export MPAN) [14][30][29].

Flat roofs differ in the mounting and in the planning limits: see solar panels on a flat roof.

How long does it take to install solar panels?

Installing solar panels takes one to two days for a typical home, and longer for a more complex system, according to the Energy Saving Trust [1]. We found no official figure for the wait from survey to installation day; MCS guidance says your quote should state how long the job will take and the expected start date [11]. The time limits that do apply are below.

Time limits and typical durations for a home solar installation, from the sources named, read 13 October 2026. Network approval times are processing targets, not the total wait.
StageTimeSource
Installation, including the electrical workone to two days for a typical system, longer if complexEnergy Saving Trust guide [1]
Cancelling a contract signed at home or at a distancefrom signing until 14 days after the last equipment is deliveredConsumer Contracts Regulations 2013; RECC Consumer Code [17][18][15]
Network approval (G99 only)10 days or less on the fast track (some battery systems); 45 days otherwiseEnergy Networks Association guide; processing targets [24]
Telling the network operator (G98)within 28 days of commissioningEngineering Recommendation G98 [25][24]
MCS certificate, current schemewithin 10 working days of commissioningMIS 3002 version 6.0 [3]
MCS certificate, redeveloped schemewithin 30 calendar days of commissioningMCS Installer Operating Requirements [6]
Building regulations certificate, England, competent person scheme installerwithin 30 days of completionBuilding Regulations 2010, regulation 20 [22]

Does the network operator need to approve it first?

Only for larger systems. The test is the total rated AC output of the generating equipment at the property: the solar inverter plus any battery with its own inverter. A battery that shares a hybrid inverter with the panels counts through that inverter's rating, not on top of it [25][2][24]. The limit is 16 amps per phase, which is 3.68 kW on an ordinary single-phase supply or 11.04 kW on three-phase [25]. Under that, the installer fits the system and tells the network operator within 28 days of switching it on (the G98 process) [24]. Above that, the G99 process applies and the network operator is consulted before installation [25].

Adding a battery can take a home system over the limit: MCS gives the example of a 3 kW solar system and a 3 kW battery connected side by side to the same single-phase supply, which together need G99 [2]. The 16 amp test is about the rated AC output of the equipment, not the size of the panel array or what you export. Network operators run a fast track for some home systems with a battery (not where the battery is set up to run the house in a power cut) [24]; SSEN, for example, aims to respond within 10 working days [27]. This is the Great Britain process. Northern Ireland has its own versions, G98/NI and G99/NI, run by NIE Networks: within 16 amps per phase the installer can usually fit the system and then tell NIE Networks, and larger systems go through a separate application [26]. The Smart Export Guarantee covers Great Britain only [29].

What should you check on installation day?

On the day, check the paperwork you agreed to, the kit that goes on the roof and that you can see the system working before the installer leaves.

An installation-day checklist drawn from the MCS standards (MIS 3002 and the Customer Commitment) and the Consumer Contracts Regulations, read 13 October 2026.
CheckWhat to look for
Before work startsIf the work could affect your roof's warranty, the installer tells you in writing and gets your written agreement [3][5]. If it starts inside the cancellation period, you asked for that in writing [19].
The kitThe panels and inverter fitted match the models on your quote and the datasheets you were given [4][5].
The generation displayA display or meter shows total generation, and the standard says you should be able to read it without a tool, ladder or torch [2].
Fault alertsThe standard says there should be a way to tell you within 48 hours if the system stops or misbehaves [2]; ask how yours works.
The demonstrationSomeone shows you how the system works and what the key parts are [5].
Building controlYou know who is notifying building control; the current MCS standard says the installer makes this clear [3].

What paperwork should you get after installation?

After installation you should get an MCS certificate, a handover pack with your guarantees and, where needed, a building regulations compliance certificate and proof the network operator was told. Keep them for the life of the system [5]; under the redeveloped MCS scheme the certificates and the network proof arrive within 30 calendar days of completion [5].

Documents to keep after a solar installation, who provides them and when, from the MCS standards, consumer codes and building regulations, read 13 October 2026.
DocumentWho and whenWhy keep it
MCS certificateInstaller registers it within 10 working days (current scheme) or 30 calendar days (redeveloped scheme) of commissioningProof of certification for Smart Export Guarantee payments in Great Britain; Ofgem also accepts equivalent schemes [3][6][30][29]
Building regulations compliance certificateCompetent person scheme installer, within 30 days of completion (England)Evidence of compliance you may need when you sell [22][21]
Proof of network notification or approvalInstaller, after commissioning (G98) or before installation (G99)Shows the network operator knows the system is connected [24][5]
Handover packAt handoverKey parts list, safety guidance, maintenance schedule, manuals, guarantees and warranties [5]
Workmanship guarantee or protectionAt handoverRECC members: insurance-backed, at least 2 years, transferable [15]. Current MCS scheme: workmanship guaranteed for at least 2 years [12]. Redeveloped MCS scheme: approved financial protection with at least 6 years' cover [13]

If you cannot find your MCS certificate, the MCS helpdesk on 0333 103 8130 can tell you whether one exists. Ask the installer for a copy first: MCS issues one, for £36, only if the installer is no longer certified or no longer trading [8]. RECC members cannot hold back handover documents until you have paid in full [15].

What protects your money before installation?

RECC caps the deposit and requires it to be insured; HIES insures deposits up to a limit. Installers who belong to RECC take a deposit of no more than 25 per cent of the estimated cost, and no more than 60 per cent with any advance payment, and insure both [15]. HIES covers deposits up to 25 per cent of the contract or £5,000, whichever is lower [16]. Under the redeveloped MCS scheme, consumer code membership is optional [10], so ask the installer how your deposit is protected. Checking a quote line by line is covered in how to check a solar quote.

Do you need planning permission or building regulations approval?

Most homes do not need planning permission for roof panels, the Energy Saving Trust says [1]; the limits differ by nation, with extra restrictions for listed buildings, conservation areas and World Heritage Sites. Building regulations normally apply in England [20]. If your installer is registered with a competent person scheme, it self-certifies the work and you do not apply yourself [21]; ask which scheme it belongs to.

In England, roof panels on a house generally stay within permitted development if they stand no more than 0.2 m out from a pitched roof and no higher than the highest part of the roof (excluding any chimney), under rules that changed on 27 August 2026 [33]. Wales, Scotland and Northern Ireland set their own limits. This is not a full permission check: listed buildings, conservation areas, flat roofs and flats are covered in do you need planning permission for solar panels.

Can you install your own solar panels?

It is legal to install your own solar panels, but the Energy Saving Trust advises against fitting solar panels yourself and says a qualified electrician still has to connect them [1]. In England, a new circuit needs a building notice or approval unless a registered competent person does the work [23]. The network operator still has to be told about the system [28]. Without an MCS installer there is no MCS certificate, and Smart Export Guarantee payments need MCS or an equivalent certification [8][30].

What if something goes wrong with the installation?

Contact the installer first: MCS says 14 days is a reasonable maximum time to expect a reply [9]. If that fails, MCS is the single point of contact for complaints about MCS installers. It acknowledges a complaint within 5 working days and aims to resolve most within 8 weeks [9]. What happens next depends on your contract.

Where a dispute goes after an MCS complaint, by installer scheme and contract date, from MCS, read 13 October 2026.
Your installer and contractRoute
Redeveloped MCS schemeMCS complaint, then free alternative dispute resolution for eligible disputes, binding on the installer [9]
Current scheme, contract from 1 January 2025MCS complaint; MCS dispute resolution if the installer agrees in writing, or dispute resolution through its consumer code (RECC or HIES) [9][10]
Contract before 1 January 2025Dispute resolution through the installer's consumer code, RECC or HIES [9]

Whether the installation pays for itself is a separate question, and for some homes it does not: are solar panels worth it weighs it up, and solar panel costs gives the government price figures.

Sources

  1. Energy Saving Trust, Rooftop solar panel installation: step-by-step guide, updated 1 Oct 2026, read 13 Oct 2026
  2. MCS, MIS 3002:2025 Solar PV systems, Issue 2.0 (redeveloped scheme), 18 Mar 2026, read 13 Oct 2026
  3. MCS, MIS 3002 Solar PV systems, version 6.0 (current scheme), 18 Mar 2026, read 13 Oct 2026
  4. MCS 032:2025, solar PV and battery pre-sale performance estimate, 1 Jan 2025, read 13 Oct 2026
  5. MCS, Customer Commitment, issue 1.1 (redeveloped scheme), 8 Sep 2026, read 13 Oct 2026
  6. MCS, Installer Operating Requirements, issue 2.0 (redeveloped scheme), 8 Sep 2026, read 13 Oct 2026
  7. MCS, news: installer transition to the redeveloped scheme, 18 Jun 2026, read 13 Oct 2026
  8. MCS, MCS certificate queries, read 13 Oct 2026
  9. MCS, What to do if things go wrong, read 13 Oct 2026
  10. MCS, Complaints Policy, version 1.0, 1 Feb 2026, read 13 Oct 2026
  11. MCS, Guidance for contracts and quotations, 1 Feb 2026, read 13 Oct 2026
  12. MCS 001-1, installer certification scheme requirements, issue 4.2 (current scheme), 20 Oct 2020, read 13 Oct 2026
  13. MCS, financial protection (redeveloped scheme), read 13 Oct 2026
  14. MCS, Smart Export Guarantee (consumer page), read 13 Oct 2026
  15. RECC, Consumer Code, version 9, 1 Jul 2026, read 13 Oct 2026
  16. HIES, Code of Practice, version S, Aug 2026, read 13 Oct 2026
  17. Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 5, read 13 Oct 2026
  18. Consumer Contracts Regulations 2013, regulation 30, read 13 Oct 2026
  19. Consumer Contracts Regulations 2013, regulation 36, read 13 Oct 2026
  20. Planning Portal, Solar panels: building regulations, read 13 Oct 2026
  21. GOV.UK, Building regulations approval, read 13 Oct 2026
  22. Building Regulations 2010, regulation 20, read 13 Oct 2026
  23. Building Regulations 2010, regulation 12, read 13 Oct 2026
  24. Energy Networks Association, Distributed generation connection guides (G98 and G99), Mar 2024, read 13 Oct 2026
  25. Energy Networks Association, Engineering Recommendation G98, issue 1 amendment 7, read 13 Oct 2026
  26. NIE Networks, What is G98/NI?, read 13 Oct 2026
  27. SSEN, G99 fast track process, read 13 Oct 2026
  28. Electricity Safety, Quality and Continuity Regulations 2002, regulation 22, read 13 Oct 2026
  29. Ofgem, Smart Export Guarantee (SEG), read 13 Oct 2026
  30. Ofgem, Smart Export Guarantee: guidance for generators, Dec 2019, read 13 Oct 2026
  31. Highways Act 1980, section 169, read 13 Oct 2026
  32. Medway Council, Apply for a scaffolding and hoarding licence, read 13 Oct 2026
  33. The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896), in force 27 Aug 2026, read 12 Oct 2026